Client: Caspian Drilling Company
Date: July 2018
Location: “Satti” rig
Work scope: Satti Jack UP Rig Project – Derrick Reconstruct
4 man rope access team and API derrick inspector carried out API RP 4G CAT 111 Derrick inspection for CDC
The inspection team carried out a visual assessment while the rig was in maintenance mode. Regular inspections are highly recommended particularly if the derrick is subject to the upper range of its load limit. Or if the structure has been subjected to critical conditions which could affect safe performance.
December 2019
5 man rope access rig building team to complete the installation off various drilling equipment on the Satti for CDC
Remove Traveling Block & De-String
Remove Fastline Stabliser Kite
Remove Finger Boards
Remove Level 3 Platforms & BHA Fingers
Remove Crown Assembley
Remove Stabbing Board & Winch Frame
Remove Choke & Kill Manifolds
Remove Mud & Cement Manifolds
Remove Bug Blower On-Top Of Dog House
Remove Wire-Line Unit
Remove ST-80 Iron Ruffneck (On Hold For Transport Frame)
Remove Monkey Board
Remove Drill Line Spooler
Remove Deadline Anchor
Remove Deadline Deflector Sheave